Hi,
I have the below code in M that gives the number of days between the start date and end date (it works fine):
[EndDate]-[StartDate]
But if I try to subtract "1" then I get an error:
[EndDate]-[StartDate]-1
I assume it's because [EndDate] and [StartDate] are stored as dates but "1" is an integar? Please do you know how to fix?
Thanks,
CM
Solved! Go to Solution.
Replace 1 by: #duration(1,0,0,0)