Query Editor / M code for subtracting one day

Hi,

 

I have the below code in M that gives the number of days between the start date and end date (it works fine):

[EndDate]-[StartDate]

 

But if I try to subtract "1" then I get an error:

[EndDate]-[StartDate]-1

 

I assume it's because [EndDate] and [StartDate] are stored as dates but "1" is an integar? Please do you know how to fix?

 

Thanks,

 

CM

1 ACCEPTED SOLUTION
MarcelBeug
Community Champion
Community Champion

Replace 1 by: #duration(1,0,0,0)

 

Specializing in Power Query Formula Language (M)

View solution in original post

1 REPLY 1
MarcelBeug
Community Champion
Community Champion

Replace 1 by: #duration(1,0,0,0)

 

Specializing in Power Query Formula Language (M)

Helpful resources

Announcements
March Fabric Community Update

Fabric Community Update - March 2024

Find out what's new and trending in the Fabric Community.

Fabric Community Conference

Microsoft Fabric Community Conference

Join us at our first-ever Microsoft Fabric Community Conference, March 26-28, 2024 in Las Vegas with 100+ sessions by community experts and Microsoft engineering.

Fabric Partner Community

Microsoft Fabric Partner Community

Engage with the Fabric engineering team, hear of product updates, business opportunities, and resources in the Fabric Partner Community.