Register now to learn Fabric in free live sessions led by the best Microsoft experts. From Apr 16 to May 9, in English and Spanish.
Hi,
I have the below code in M that gives the number of days between the start date and end date (it works fine):
[EndDate]-[StartDate]
But if I try to subtract "1" then I get an error:
[EndDate]-[StartDate]-1
I assume it's because [EndDate] and [StartDate] are stored as dates but "1" is an integar? Please do you know how to fix?
Thanks,
CM
Solved! Go to Solution.
Replace 1 by: #duration(1,0,0,0)
Replace 1 by: #duration(1,0,0,0)
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
109 | |
98 | |
77 | |
66 | |
54 |
User | Count |
---|---|
144 | |
104 | |
100 | |
86 | |
64 |