Allocate values by months

Hi All.

 

Please help with tip for calculate cost allocation by months with accumulation.

 

Now i have this data set :

 

image.png

 

I need create visualization in Power BI  - transpose data and calculate accumulation value with summarize by month. 

For example :

 

image.png

 

Project life 12 month, cost will be allocate to 12 equals parts.

 
5 REPLIES 5
Greg_Deckler
Super User
Super User


Take a look at these two Quick Measures as I think you want something like them.

https://community.powerbi.com/t5/Quick-Measures-Gallery/Open-Tickets/m-p/409364
https://community.powerbi.com/t5/Quick-Measures-Gallery/Periodic-Billing/m-p/409365


Follow on LinkedIn
@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...

Hi Dear.

 

No this is no helpful for me 😞

 

I need allocate them.

Can you post your sample data as text? I don't want to type all of that.


Follow on LinkedIn
@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...

yup 

 

 

NumberStart dateEnd dateCost

Project 101.09.201931.08.202052,3
Project 201.02.201931.01.202045,4
Project 301.04.201931.03.202046
Project 401.01.202031.12.202053,5
Project 501.07.201930.06.202051,1
Project 601.09.202031.08.202153,4
Project 701.01.201931.12.201946,7
Project 801.09.202031.08.202161,2
Project 901.03.202028.02.202152,1
Project 1001.03.202028.02.202155,2
Project 1101.06.201831.05.201935
Project 1201.06.201831.05.201988
Project 1301.02.201831.01.201946
Project 1401.03.201828.02.201912
Project 1501.04.201831.03.201922

up

Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

MayPowerBICarousel

Power BI Monthly Update - May 2024

Check out the May 2024 Power BI update to learn about new features.

LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.