Earn a 50% discount on the DP-600 certification exam by completing the Fabric 30 Days to Learn It challenge.
Is there a place to log features/bugs with the Gantt Chart visualization? If not here are my suggestions:
1) I need a way to control the date scale. Instead of by day, I would like to see it by Month.
2) I would like to display the Task Name either in the bar or besides the bar instead of in a column to the right.
@RobCannon If you need to send feedback go to app.powerbi.com/visuals and when you select the custom visual card below there is a "Contact Author".
They are really quick in responding.
Regarding the options that you like to suggest there are already there.
1) I need a way to control the date scale. Instead of by day, I would like to see it by Month.
On the properties of the you can change from Days/MOnths/Weeks/Years..property name is "Gantt Chart Type"
2) I would like to display the Task Name either in the bar or besides the bar instead of in a column to the right.
For this one you need to add the field with the "Task Name" also in Resource field holder and then change "Category Label" to off..This way you will have task names besides the bars and no task name on the right. ( red arrow in picture)
Thanks for the reply. I saw the "Gantt Chart Type", but it didn't work. I tried updating the visualization (to v0.30) and that works great!
The label to the side doesn't quite work becuase the text is cut off. I will make a suggestion to the author to be able to put the label in the bar.
Why are the task names cut short? Annoying