Scoring overall completion

I have Table A with Workpack List. Table B shows link of Work pack to documents with their status 'Completed" or "In progress". I want to have a visual which give me the completion score of each work pack. if all documents linked to a work pack are completed, the workpack score is 100%. example as below.

 

Table1  Table2    Report   
Workpack  WorkpackDocDoc StatusForecast Date WorpackOverall Status    Doc Count latest Doc date
A  AFFComplete  A100%4 
B  AGGComplete  B25%515/10/2023
   AHHComplete      
   BRRComplete      
   BHHIn Progress5/05/2023     
   BTTComplete      
   BOOIn Progress10/05/2023     
   BPPIn Progress15/10/2023     
1 ACCEPTED SOLUTION
Ahmedx
Super User
Super User

1) the number of documents A will be 3, not 4
2) the number of documents B will be 5, but here the number is Complete will be 2, and therefore the percentage will be 40%, but not 25%
Sample PBIX file attached
https://1drv.ms/u/s!AiUZ0Ws7G26Rh2PwawPkeSg4hmLQ?e=QoejU4

Screen Capture #1004.png

View solution in original post

2 REPLIES 2
Ahmedx
Super User
Super User

1) the number of documents A will be 3, not 4
2) the number of documents B will be 5, but here the number is Complete will be 2, and therefore the percentage will be 40%, but not 25%
Sample PBIX file attached
https://1drv.ms/u/s!AiUZ0Ws7G26Rh2PwawPkeSg4hmLQ?e=QoejU4

Screen Capture #1004.png

Thanks for the help!

Helpful resources

Announcements
LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.