Hi all,
We have created a planning in Project Online, our planning is for a long project with a lot of diferents tasks. Then we need to monitor the tasks in detail.
I have already conect with the data, and i can read the values of % and de %planned, but % completed is a temporal value in that moment i would like to record when someone upload the value of the % completed to be able to graph how is going the project.
It is possible?
Thanks!
Anxo
I'm not sure if there's any column recording the "increment" amount of entire project uploaded by each individual user in Project Online datasets. If there's no such column at that detail level, it's not possible to achieve your goal.
You may ask this question on ProjectOnline Forum:
https://social.technet.microsoft.com/Forums/projectserver/en-US/home?forum=projectonline