Project Online custom report

Hi all,

 

We have created a planning in Project Online, our planning is for a long project with a lot of diferents tasks. Then we need to monitor the tasks in detail.

I have already conect with the data, and i can read the values of % and de %planned, but % completed is a temporal value in that moment i would like to record when someone upload the value of the % completed  to be able to graph how is going the project.

 

It is possible? 

 

 Thanks!

Anxo

 

1 REPLY 1
v-sihou-msft
Employee
Employee

@abernardez

 

I'm not sure if there's any column recording the "increment" amount of entire project uploaded by each individual user in Project Online datasets. If there's no such column at that detail level, it's not possible to achieve your goal. 

 

You may ask this question on ProjectOnline Forum:

https://social.technet.microsoft.com/Forums/projectserver/en-US/home?forum=projectonline

 

Regards,

Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

MayPowerBICarousel

Power BI Monthly Update - May 2024

Check out the May 2024 Power BI update to learn about new features.

LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.