I have Power BI connected to Microsoft Project through PWA and for the projects I am managing I am trying to see how much work a resource has in a given month. Project tasks only have a start date and an end date and pulling one of those won't show the full picture for any month in between those two months. Below is what I am looking for:
Data Example:
Desired Result:
@bcummings12345 , You try if my blog can help
Static Method : https://amitchandak.medium.com/power-bi-power-query-vs-dax-months-between-range-df019cec823b