Hi @Anonymous,
If I understand your requirement correctly that your want to show the previous quarters data when select this Quarter.
If it is, here is a sample I created. I create a Date table with Calendar function and create the measure with below.
Measure = CALCULATE(SUM(Table1[Sales]),DATEADD('Date table'[Date],-1,QUARTER))
More details, please refer to the attachment.
If you still need help, please share your data sample and your desired output so that we could help further on it.
Best Regards,
Cherry
Hi
The solution by work well when comparing whole quarter, but in practice 90% of the time we want to compare a period parallel to the dates in the specified dates column. I will suggest you to use PARELLEPERIOD function instead of DATEADD or DATESBETWEEN .
Measure = CALCULATE(SUM(Table1[Sales]),PARELLEPERIOD('Date table'[Date],-1,QUARTER))
Regards,
Gaurav Raj Singh
If this post helps, then please consider Accept it as the solution to help the other members find it more
@Anonymous
but i dont have any calculation. Project detail is a simple Text.
Then why I need to use calculate.
Hi @Anonymous,
If I understand your requirement correctly that your want to show the previous quarters data when select this Quarter.
If it is, here is a sample I created. I create a Date table with Calendar function and create the measure with below.
Measure = CALCULATE(SUM(Table1[Sales]),DATEADD('Date table'[Date],-1,QUARTER))
More details, please refer to the attachment.
If you still need help, please share your data sample and your desired output so that we could help further on it.
Best Regards,
Cherry
Hi @v-piga-msft
I just want to display project which have been resolved last quarter from the current date.There is no calculation.
Can you please suggest how it can be done.
Example:
Project Date resolved
A 20/01/2020
B 12/11/2019
C 11/10/2019
D 11/06/2019
Then Output should be
B
C
Hi,
Are you OK with this? You may download my PBI file from here.
Hi @Anonymous ,
Make a new column and apply SWITCH and DATESBETWEEN function.
So it should be something like
NewColumn = SWITCH(TRUE(), date < last quater first date && date > last quater last date...etc
Regards,
Gaurav
Hi @v-piga-msft,
The DAX function which you have mentioned above is correct ... even i did the same.
But it is not working fine with data which i have.
Please find below the link for the pbix file and let me know how u can achieve the same.
https://drive.google.com/file/d/11XS6xMhopJslPYGr04ryPd3PrwwDav-k/view?usp=sharing
Regards,
Karthik S
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
104 | |
101 | |
79 | |
72 | |
64 |
User | Count |
---|---|
142 | |
108 | |
101 | |
81 | |
74 |