Today Filter for Gantt Chart

Hello team,

 

Could you advise how to filter a visual by todays date (only show running events) if I have a date start and an end date in a Gantt chart?

Many thanks,

Tat

1 ACCEPTED SOLUTION
v-cgao-msft
Community Support
Community Support

Hi @Anonymous ,

Please create a measure.

Measure = IF(MAX('Table'[StartDate])<=TODAY()&&MAX('Table'[EndDate])>=TODAY(),1)

then add it to the gantt's filter.

vcgaomsft_0-1682931334447.png

 

Best Regards,
Gao

Community Support Team

 

If there is any post helps, then please consider Accept it as the solution  to help the other members find it more quickly. If I misunderstand your needs or you still have problems on it, please feel free to let us know. Thanks a lot!

How to get your questions answered quickly --  How to provide sample data in the Power BI Forum

View solution in original post

2 REPLIES 2
v-cgao-msft
Community Support
Community Support

Hi @Anonymous ,

Please create a measure.

Measure = IF(MAX('Table'[StartDate])<=TODAY()&&MAX('Table'[EndDate])>=TODAY(),1)

then add it to the gantt's filter.

vcgaomsft_0-1682931334447.png

 

Best Regards,
Gao

Community Support Team

 

If there is any post helps, then please consider Accept it as the solution  to help the other members find it more quickly. If I misunderstand your needs or you still have problems on it, please feel free to let us know. Thanks a lot!

How to get your questions answered quickly --  How to provide sample data in the Power BI Forum

Anonymous
Not applicable

Hello Gao, 

Works better than expected!

Thanks a million,

Tat
@v-cgao-msft 

Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

MayPowerBICarousel1

Power BI Monthly Update - May 2024

Check out the May 2024 Power BI update to learn about new features.

Europe Fabric Conference

Europe’s largest Microsoft Fabric Community Conference

Join the community in Stockholm for expert Microsoft Fabric learning including a very exciting keynote from Arun Ulag, Corporate Vice President, Azure Data.

Top Kudoed Authors