How to show percentage 100% untill project end date

Hello Friends,

 

I am struggling in logic on below my requirement.

My Fields are:

[Project name]

[Target Start Date] & [Target End Date]: Each project has its own start and end date like (01 Jan 2020 to 31 Dec 2022)

[Reporting Date]: Each Project has its own monthly progress untill end (end will be with 100%), and this field we are going to show in monthly wise

[Plan Progress]: Where it ends with 100% which means that project Target Ended.

Below is the example: Note::: wherever I mentioned "...." which means continution of months in that year.

Project NameJan 2020Feb 2020Mar 2020....Jan 2021Feb 2021....Jan 2022Feb 2022....
A10%15%20%....100% ....   
B5%10%15%....65%75%....100%  
C5%10%15%....45%50%....75%  

 

Now my requirement is whatever projects ended with 100%, I should show 100% for rest all rows untill long tenure project meets 100%.

example. A ended at Jan 2021 but C ends at Jan 2023. so, whatever projects are already ended those all show 100% untill C project end date.

 

Kindly, help me on this complex requirement.

 

Regards,

 

Babu

2 REPLIES 2
v-easonf-msft
Community Support
Community Support

Hi,  @Anonymous 

Could you please tell me whether your problem has been solved?

Best Regards,
Community Support Team _ Eason

amitchandak
Super User
Super User

Please check if this can help you

https://community.powerbi.com/t5/Community-Blog/HR-Analytics-Active-Employee-Hire-and-Termination-tr...

 

Can you share sample raw data. If possible please share a sample pbix file after removing sensitive information.Thanks.

My Recent Blog -

https://community.powerbi.com/t5/Community-Blog/HR-Analytics-Active-Employee-Hire-and-Termination-tr...

 

Appreciate your Kudos. In case, this is the solution you are looking for, mark it as the Solution.
In case it does not help, please provide additional information and mark me with @

Thanks. My Recent Blogs -Decoding Direct Query - Time Intelligence, Winner Coloring on MAP, HR Analytics, Power BI Working with Non-Standard TimeAnd Comparing Data Across Date Ranges
Connect on Linkedin

Helpful resources

Announcements
LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.