cmontoure22
Frequent Visitor

Create a Forecast graph of the hours/FTE per month given project start date, end date and hours

Hello -

I'm looking to Forecast the number of Full Time Equivalent (FTE) of work given a list of Project Data: Start Date, End Date and Total Project Hours. The Green Columns below are what would be the inputs. I believe I need to:

  • Calculate the working days between Start Date and End Date
  • Distribute the hours per month by on the # of working each month
  • The two graphs below would be the output I'm looking for.

Thoughts on the approach to this?

cmontoure22_0-1693514217108.png

 

2 REPLIES 2
amitchandak
Super User
Super User

@cmontoure22 , for work day you use networkdays

 

Power BI - Business day with and without using DAX Function NETWORKDAYS: https://www.youtube.com/watch?v=Qs03ZZXXE_c
https://medium.com/@amitchandak/power-bi-dax-function-networkdays-5c8e4aca38c

 

For Business hours

https://exceleratorbi.com.au/calculating-business-hours-using-dax/

 

To distribute use this, use networkdays to get days of month and use filter of workday

 

Power BI Distributing/Allocating the Monthly Target(Convert to Daily Target): Measure ( Daily/MTD): https://community.powerbi.com/t5/Community-Blog/Power-BI-Distributing-Allocating-the-Monthly-Target-...

 

If this does not help
Can you share sample data and sample output in table format? Or a sample pbix after removing sensitive data.

Hello-

 

Thanks for that. I have the NETWORKING days working. If I multipy that times 8 = Net Working Hrs.

 

Each month's Net Working Hrs will equate to 1 FTE

 

How do I distribute Each Projects Total hours over each month between the Start and End Dates?

 

Each Project's Hours are based on Table 2 below by connecting theType and Size between each Table.

 

 

The goal is to get this this output, that can be filtered by Project Name, Type or Size

cmontoure22_0-1693598361025.png

 

Project Info (Table 1)

Start DateEnd DateProject nameProject TypeSizing
1/1/2310/1/23Project 1Type 1XL
2/1/2310/1/23Project 1Type 2XL
3/1/2310/1/23Project 1Type 3XL
4/1/2310/1/23Project 1Type 4XL
5/1/2310/1/23Project 1Type 5XL
6/1/2310/1/23Project 1Type 6XL
4/1/233/1/24Project 2Type 1XL
6/1/233/1/24Project 2Type 2XL
8/1/233/1/24Project 2Type 3XL
4/1/246/1/24Project 2Type 4XL
4/1/246/1/24Project 2Type 5XL
1/1/245/1/24Project 3Type 1XL
1/1/246/1/24Project 3Type 2XL
1/1/247/1/24Project 3Type 3XL

 

Sizing (Table 2)

Project TypeSizingHours
Type 1XL500
Type 2XL250
Type 3XL500
Type 4XL500
Type 5XL1250
Type 6XL1250

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.