hjmoon
New Member

Can't schedule refresh for semantic model error

hjmoon_0-1705337974738.png

I got this error message which doesn't even mention which data source is the problem. I will say this is the report A.
Report A used to work without any problem until last week when we changed one of the data source to stored procedure.
As a test, I deployed the exactly same Power Bi desktop file as Report A with different name (Report B) to the same work space and it works without any error. Gateway option is enabled, scheduled refresh is enabled as usual. 

Even when I tried to deploy the completely different report with same name as Report A, the error message never disappears.
What am I supposed to do?  Has anyone faced the same problem before?

1 ACCEPTED SOLUTION
v-tianyich-msft
Community Support
Community Support

Hi @hjmoon ,

 

When you change the datasource stored procedure, its credentials need to be republished to the service for use via power bi desktop, otherwise it will be treated as an unsupported datasource type.

 

Hope it helps!

 

Best regards,
Community Support Team_ Scott Chang

 

If this post helps then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

1 REPLY 1
v-tianyich-msft
Community Support
Community Support

Hi @hjmoon ,

 

When you change the datasource stored procedure, its credentials need to be republished to the service for use via power bi desktop, otherwise it will be treated as an unsupported datasource type.

 

Hope it helps!

 

Best regards,
Community Support Team_ Scott Chang

 

If this post helps then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.