After import CSV data to PBI , Date field how to remove the red mark ?

Hi All

After load at PBI , it does show 1 error , when i look at PQ , the Date field have red dot , how to clear ?

admin11_0-1613784570533.png

 

1 ACCEPTED SOLUTION
PhilipTreacy
Super User
Super User

@admin11 

Hi Paul,

Just be aware that removing the error(s) removes the entire row that error appears in.  If you don't want that then you'll need to fix the cause of the error which may be an incorrectly formed date value.

regards

Phil



Did I answer your question? Then please mark my post as the solution.
If I helped you, click on the Thumbs Up to give Kudos.


Blog :: YouTube Channel :: Connect on Linkedin


Proud to be a Super User!


View solution in original post

2 REPLIES 2
PhilipTreacy
Super User
Super User

@admin11 

Hi Paul,

Just be aware that removing the error(s) removes the entire row that error appears in.  If you don't want that then you'll need to fix the cause of the error which may be an incorrectly formed date value.

regards

Phil



Did I answer your question? Then please mark my post as the solution.
If I helped you, click on the Thumbs Up to give Kudos.


Blog :: YouTube Channel :: Connect on Linkedin


Proud to be a Super User!


ryan_mayu
Super User
Super User

@admin11 

select that column and remove errors

1.png





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




Helpful resources

Announcements
LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.