Hello,
I'm looking for the correct DAX measure of how to return the correct budget by having following condition.
This is an example of the report period and expected corresponding budget value.
...
I'm grateful for any tips on how I can get this PowerBI DAX measure to work, on these expected conditions.
Hi @geirselvag ,
The data you gave is not comprehensive enough, I hope you can explain to me your desired output. For example, the data for 2023-03 is clearly only PRO 10,how did you get PRO 11? And why does Current value exist in baseline of 2023-06?
How to Get Your Question Answered Quickly
If it does not help, please provide more details with your desired output and pbix file without privacy information (or some sample data) .
Best Regards
Community Support Team _ Rongtie
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @v-rongtiep-msft,
Thank you for reaching out for assistance, I appreciate that.
Detailed explaination of desired output.
The process for the projects is that they can have multiple re-baselines during it's lifetime. Example when a project is initiated, we get two datasets "Current" in one table 'CurrentBudget' and copy of this dataset as "CCE1" to another table 'Baseline'. When there is no re-baseline (e.g only "CCE1"), the desired output will always be "Current" or first baseline regardless of what reporting period is selected.
When creating first baseline ("2023-01") for PRO10, we have two same datasets ("CCE1"="Current") until next re-baseline is being created. Store all previous baseline's with period "yyyy-mm" and baseline "CCEx" as reference. Since there are two baseline (e.g "Current" <> "CCE1"), this mean desired output when select report period "2023-01", "2023-02", "2023-03", "2023-04", "2023-05" will then be "CCE1" from first baseline with the value 10,000.
When report period "2023-06" is selected or after the desired output is "Current" (ref. "CCE2") with value 15,000 . After the last re-baseline (e.g "2023-06", "CCE2"), we always want desired output to be "Current" which is the same/copy to "Baselineof "CCE2".
The project "PRO11" has only one baseline, therefore from "2023-03" the desired output of this project is "Current" from "2023-03" to "2023-12". The table 'Baseline' includes baseline for several projects with the same process.
Hopefully, this is useful information on how we need desired output to be. Thank you for any tips of how to make this possible in a Power BI DAX measure.