I was trying to replicate the below excel bar chart in Power BI but couldnt find a way.
X axis as dates
Y axis as Project A , B, C names
3 Bars start with start dates and followed with recruiment, training, probation in the same bar but with different colors and value(days) within the bar.
Lastly, add today's date as dotted line on the chart.
Any tips?
Project Name | Start Date | Recruitment (days) | Training(days) | Probation (days) |
Project A | 09/01/2022 | 30 | 30 | 30 |
Project B | 10/01/2022 | 20 | 40 | 30 |
Project C | 11/01/2022 | 30 | 30 | 30 |
Or you can use white bars and DATEDIFF with MIN([Start Date])
You can use this example with visualization for it.
shorturl.at/kuANU