Linnil
Helper II
Helper II

Let Statement (Step) with IF Statement

Hi everyone - I'm just learning how to make Let Statements as Steps.

I have this problem - I'm calculating Years of Service, at 30 Apr 23.

However, if the person has left / if Status is T, then the endDate = Term Date.

Is it possible to modify the statement below so it does a check for the endDate ?

 

This is my Let Statement (as a Step) so far:

let
startDate = [Hire Date],
endDate = #date(2023,04,30),
durationInDays = Duration.Days(endDate - startDate),
durationInYears = durationInDays / 365
in
durationInYears

 

I thought briefly about doing it as a conditional column, I think that's another complication.

 

Thanks for any suggestions 🙂

1 ACCEPTED SOLUTION
m_dekorte
Super User
Super User

Hi @Linnil 

 

Assuming you have a [Status] and [Term Date] field, like [Hire Date] in in your table, try this:

 

let
    startDate = [Hire Date],
    endDate = if [Status] = "T" then [Term Date] else #date(2023,04,30),
    durationInDays = Duration.Days(endDate - startDate),
    durationInYears = durationInDays / 365
in
    durationInYears

 

 

I hope this is helpful

View solution in original post

2 REPLIES 2
m_dekorte
Super User
Super User

Hi @Linnil 

 

Assuming you have a [Status] and [Term Date] field, like [Hire Date] in in your table, try this:

 

let
    startDate = [Hire Date],
    endDate = if [Status] = "T" then [Term Date] else #date(2023,04,30),
    durationInDays = Duration.Days(endDate - startDate),
    durationInYears = durationInDays / 365
in
    durationInYears

 

 

I hope this is helpful

Thank you for this! (sorry for late reply, it was a crazy week).
Have a lovely weekend 🙂

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors
Top Kudoed Authors