Hello,
I am trying to expose Project Online Baseline data in a report in PowerBI. Whilst I can connect to the odata feed at https://contoso.sharepoint.com/sites/pwa/_api/ProjectData/ProjectBaselines, this only seems to display the main baseline data. I need to also show Baseline1 Work, Baseline1 Cost, Baseline2 Work, Baseline2 Cost, etc, however I can't seem to figure out how to get this data. I'm probably missing something obvious but I can't see it!!
I was really hoping to modiify a version of the reports in the Project Online Content Pack (latest) to show this as an additional report.
Any help would be appreciated.
Thanks
Kelvin
Hello i have the same issue. Couldnt find datasource for other baseline info (Baseline 1 , Baseline 2 ) other than the default baseline.
You may do research into The Advanced Editor.
Hi Sam,
Many Thanks - I will look into this further.....
Thanks
Kelvin
Hi Sam,
I looked at the Advanced Editor but this only shows the syntax of the query. It doesn't show me where to find the Baseline1 Work, Baseline1 Cost, etc fields. What I am looking for is the actual data source where these might reside in Microsoft Project Online. Any ideas on the data source that might host these fields ?
Thanks
Kelvin