Hi all,
i have on the canvas a YEAR and MONTH Slicer and the following two measures which i compare:
Solved! Go to Solution.
Hi @Pikachu-Power
The NEXTYEAR function always returns a full year of dates.
You can try instead :
Plan_YTD_NY = CALCULATE([Plan_YTD], PARALLELPERIOD(Calender[Date], 1, YEAR))
Have a good day,
Cado
Hi @Pikachu-Power
The NEXTYEAR function always returns a full year of dates.
You can try instead :
Plan_YTD_NY = CALCULATE([Plan_YTD], PARALLELPERIOD(Calender[Date], 1, YEAR))
Have a good day,
Cado
Ok Thank you! PARALLELPERIOD with "12 MONTH" instead of "1 YEAR" helps.