Register now to learn Fabric in free live sessions led by the best Microsoft experts. From Apr 16 to May 9, in English and Spanish.
Hi,
I have a sql server 8.00.818 (this is a legacy setup and cannot be upgraded to latest versions) setup but unable to get powerbi to refresh from this server on regular basis as it fails saying there is an issue with the credentials, but when checking the gateway and datasources these are fine.
So I setup a test on a sql express 14.0.1000 setup which pulls the data from the original server and then I have powerbi use the sql express database and this works fine with no issues with a scheduled refresh, but as I can't configure jobs scheduled jobs within sql express I thought I would try getting it to work with a sql server 9.00.5266.00 setup, which I know is still an older version of SQL, but again I still get the issues with the credentials.
Is there a limitation of what version of sql can be used with power bi to successfully refresh data.
thanks
Solved! Go to Solution.
Hi @v-danhe-msft,
The issue with the credentials is that PowerBI say they are incorrect, even though the same credentials work via the desktop app and authenticate ok in the datasource in the gateway.
the 'i can't configure scheduled jobs within sql express' litterally means that, within sql express you cannot setup scheduled jobs to run on a regular basis like you can on sql enterprise editions. A solution I will need to do is setup a scheduled task to run a script
I since found out the issues are to do with PowerBI and that you cannot use sql versions prior to 2005 for direct queries and this is the reason why the authenication is failing, it would be better if powerbi gave you a more informative response that was related to this issue.
Hi @mmorley,
Could you please post the problem with the crendials and could you check if you could refresh your data in Power BI Desktop?
And I could not understand the sentence "I can't configure jobs scheduled jobs within sql express", could you please offer more information about the 'jobs' and 'scheduled jobs'?
Regards,
Daniel He
Hi @v-danhe-msft,
The issue with the credentials is that PowerBI say they are incorrect, even though the same credentials work via the desktop app and authenticate ok in the datasource in the gateway.
the 'i can't configure scheduled jobs within sql express' litterally means that, within sql express you cannot setup scheduled jobs to run on a regular basis like you can on sql enterprise editions. A solution I will need to do is setup a scheduled task to run a script
I since found out the issues are to do with PowerBI and that you cannot use sql versions prior to 2005 for direct queries and this is the reason why the authenication is failing, it would be better if powerbi gave you a more informative response that was related to this issue.
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.