Assignment Hours Estimated in MS Project =8
Resource Worked and Reported in PWA =4
Remaining Work =0
The Assignment hours for the resource was 8 hours. The resource completed the work 100% in 4 hours instead of 8 hours. There is no remaning work.
My problem is that the content pack for MS Project Online is not reporting the actual hours of (4 hours) worked. It continues to show the original 8 hours in Power BI.
Help and Thanks,
Kerry
Hi @Kerry4 ,
Didi you found a solution for this problem ? I have the same and I don't konw how I can solve it by using Assignment Actual Work.
Please Help
HI @Kerry4,
How did you configure refresh options, can you please share more detail information to help use clarify your scenario?
How to Get Your Question Answered Quickly
In addition, did these data update in project online? If not I think this issue should more related to project online it self.
You can also take a lookt at following link:
Tune Project Online performance
Regards,
Xiaoxin Sheng