PWA and Power BI- Actual Hours not updating

Assignment Hours Estimated in MS Project  =8

Resource Worked and Reported in PWA  =4

Remaining Work =0

 

The Assignment hours for the resource was 8 hours.  The resource completed the work 100%  in 4 hours instead of 8 hours.  There is no remaning work. 

 

My problem is that the content pack for MS Project Online is not reporting the actual hours of (4 hours) worked.  It continues to show the original 8 hours in Power BI.

 

Help and Thanks,

Kerry

2 REPLIES 2
Anonymous
Not applicable

Hi @Kerry4 ,

 

Didi you found a solution for this problem ? I have the same and I don't konw how I can solve it by using Assignment Actual Work.

Please Help

v-shex-msft
Community Support
Community Support

HI @Kerry4,

 

How did you configure refresh options, can you please share more detail information to help use clarify your scenario?

How to Get Your Question Answered Quickly

 

In addition, did these data update in project online? If not I think this issue should more related to project online it self.

You can also take a lookt at following link:

Tune Project Online performance

 

Regards,

Xiaoxin Sheng

Community Support Team _ Xiaoxin
If this post helps, please consider accept as solution to help other members find it more quickly.

Helpful resources

Announcements
April AMA free

Microsoft Fabric AMA Livestream

Join us Tuesday, April 09, 9:00 – 10:00 AM PST for a live, expert-led Q&A session on all things Microsoft Fabric!

March Fabric Community Update

Fabric Community Update - March 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors
Top Kudoed Authors