Migrate gateway to new server - best practices?

Hi, we need to migrate our Enterprise gateway from a development VM to a dedicated new gateway VM. What is the best process for this?

 

We already have live users using the existing gateway with several reports / dashbaords so need to be as prepared as possible to minimize downtime. Ideally we want to avoid having to republish reports etc.

 

I believe we do have the recovery key if/when needed.

 

 

 

1 ACCEPTED SOLUTION

@Anonymous All you should need to do is install a new gateway on the new VM and use the recovery key and the gateway will pick up the load of everything using it in the Service.


Looking for more Power BI tips, tricks & tools? Check out PowerBI.tips the site I co-own with Mike Carlo. Also, if you are near SE WI? Join our PUG Milwaukee Brew City PUG

View solution in original post

5 REPLIES 5
v-shex-msft
Community Support
Community Support

HI @Anonymous,

 

I agree with Eno1978's point of view, re-install and sign in the original gateway is the simply method to migrate gateway.

In addition, you can also install a new gateway in that server, then add original data sources to this gateway.

After these steps, you can choose to use which gateway to refresh.

 

Regards,

Xiaoxin Sheng

Community Support Team _ Xiaoxin
If this post helps, please consider accept as solution to help other members find it more quickly.

Hi Xiaoxin,

 

Is there any easy way to copy the existing data sources then restore them to the new gateway?

 

Thanks,

Gary

I wouldn't classify it as "easy," but using PowerShell you can automate the process:

 

https://docs.microsoft.com/en-us/rest/api/power-bi/gateways/createdatasource

 

Cheers,
Adolfo

Connect with me in LinkedIn: https://pr.linkedin.com/in/adolfosocorro
Follow me on Twitter: https://twitter.com/AdolfoSocorro

@Anonymous All you should need to do is install a new gateway on the new VM and use the recovery key and the gateway will pick up the load of everything using it in the Service.


Looking for more Power BI tips, tricks & tools? Check out PowerBI.tips the site I co-own with Mike Carlo. Also, if you are near SE WI? Join our PUG Milwaukee Brew City PUG
Anonymous
Not applicable

Thanks for this. Completed this today and it worked as you suggested it would.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors
Top Kudoed Authors