Hi community.

 

I have two columns in my excel worksheet with two types of  dates. 

 

#1 starting date of the work

#2 End date of the work.

 

I need to calculate how many days has passed since the work started but the end date must be blank (this means that the work has not finished yet)

 

any ideas?

 

Thanks!

1 ACCEPTED SOLUTION

Accepted Solutions
Washivale Regular Visitor
Regular Visitor

Re: Calculating Days Between

Hi There,

 

you can use following formula to calculate number of days passed since work Started.

 

i am assuming start date is in column B, and End Date is in Column C

 

enter Number of days in Column D as follow

 

=If(C2="", Today()-B2,C2-B2)

 

convert column format to General

 

Explanation 

C2=""  This part of formula will check if end date is blank, if it is blank if condition will return true and below condition will run

 

Today()- B2 : Today() will return todays date and Start date will be substracted from Todays date.

 

if End date is present then C2-B2 will return days passed between Start and End Date.

 

if you dont wish to calculate days for work finished records, you can use below formula

 

=If(C2="", Today()-B2,"")

 

let me know if it works!

 

Thank You

View solution in original post

1 REPLY 1
Washivale Regular Visitor
Regular Visitor

Re: Calculating Days Between

Hi There,

 

you can use following formula to calculate number of days passed since work Started.

 

i am assuming start date is in column B, and End Date is in Column C

 

enter Number of days in Column D as follow

 

=If(C2="", Today()-B2,C2-B2)

 

convert column format to General

 

Explanation 

C2=""  This part of formula will check if end date is blank, if it is blank if condition will return true and below condition will run

 

Today()- B2 : Today() will return todays date and Start date will be substracted from Todays date.

 

if End date is present then C2-B2 will return days passed between Start and End Date.

 

if you dont wish to calculate days for work finished records, you can use below formula

 

=If(C2="", Today()-B2,"")

 

let me know if it works!

 

Thank You

View solution in original post

Helpful resources

Announcements
Can You Solve These Challenge

Challenge: Can You Solve These?

Find out how to participate in the first Power BI 'Can You Solve These?' challenge.

Community News & Announcements

Community News & Announcements

Get your latest community news and announcements.

Virtual Launch Event

Microsoft Business Applications October Virtual Launch Event

Join us for an in-depth look at the new innovations across Dynamics 365 and the Microsoft Power Platform.

Community Kudopalooza

Win Power BI Swag with Community Kudopalooza!

Each week, complete activities and be qualified in the drawing for cool Power BI Swag.

Users Online
Currently online: 100 members 1,476 guests
Please welcome our newest community members: