Hi,

 

We currently have a P1 premium capacity. We are utilising deployment pipelines within our capacity resulting in environment workspaces (DEV and TEST) sometimes containing unwanted capacity draining resources. We purchased some PPU licenses to isolate these troublesom workspaces but without usage metrics on the PPU workspaces it was hard to determine if these would again cause issues moving back into our premium capacity or not. Is the best strategy to purchase another P1 capacity for DEV and TEST content so the PROD capacity isn't effected or would a P2 be enough here? Any other options?

 

Thanks.

1 ACCEPTED SOLUTION

You can split a P2 into two P1 but then you end up having the same performance issues again. A better approach (if you can afford it) is to use two or more P2 or higher. For example our Finance team has a dedicated P4 for production and a P3 as Dev/DR.

View solution in original post

3 REPLIES 3
lbendlin
Super User
Super User

P2 has double the capacity of a P1.

 

And yes, getting extra P1s (at the minimum)  is the right thing to do if you can afford it.

Thanks for your reply. Can a P2 be split to keep Dev and Test workspaces away from Prod?

You can split a P2 into two P1 but then you end up having the same performance issues again. A better approach (if you can afford it) is to use two or more P2 or higher. For example our Finance team has a dedicated P4 for production and a P3 as Dev/DR.

Helpful resources

Announcements
November 2022 Update

Check it Out!

Click here to read more about the November 2022 updates!

Microsoft 365 Conference â__ December 6-8, 2022

Microsoft 365 Conference - 06-08 December

Join us in Las Vegas to experience community, incredible learning opportunities, and connections that will help grow skills, know-how, and more.

Top Solution Authors