PBI - Timescheduling with steps

Hi,
we use the PBI Report Server Version and we have one time schedule to start our daily morning refresh.

Now we have many dashoards and therefore some reports are not refreshed, because they get an TimeOut.

I know about the Timeout Configuration.

 

My question - is it possible, to create TimeSchedules based on another Steps?

Maybe - all Reports for one TimeSchedule are finished then start the next one?

 

Thankes for the help

 

Armin 

1 ACCEPTED SOLUTION
d_gosbell
Super User
Super User


@Anonymous wrote:

My question - is it possible, to create TimeSchedules based on another Steps?

Maybe - all Reports for one TimeSchedule are finished then start the next one?

 


No this is not possible, the schedules are simple time based triggers, there is no workflow

View solution in original post

2 REPLIES 2
d_gosbell
Super User
Super User


@Anonymous wrote:

My question - is it possible, to create TimeSchedules based on another Steps?

Maybe - all Reports for one TimeSchedule are finished then start the next one?

 


No this is not possible, the schedules are simple time based triggers, there is no workflow

Anonymous
Not applicable

Thanks for the info - even if it doesn't make me happy 

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.