Hi Community,
I am currently calculating my project status in excel.
Example in Excel:
on time = planned End date
delayed 1-3 month = planned End date + 90 days
delayed 3-6 month = planned End date + 180 days
I would like to do this calculation directly in the power bi to maintain my status
does someone have a solution?
You should be able to complete this using the DATEADD calculation as long as your dates are in the date format and you have a good date dimension table. If your columns in your source are named as the sample, try:
on time = [planned End date]
delayed 1-3 month = DateAdd( [planned End date], 90, day)
delayed 3-6 month =DateAdd( [planned End date], 180, day)
See this link for more information.
Proud to be a Super User!
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
117 | |
104 | |
77 | |
73 | |
52 |
User | Count |
---|---|
145 | |
109 | |
109 | |
90 | |
64 |