po
Post Prodigy
Post Prodigy

chart to show activity over 24 hours

Hi,

 

Have folloiwng table

 

activity, start time, end time, amount processed

joba, 00:00:01        23:59:00, 200

jobb, 15:00:00             18:00:00, 400

jobc   18:00:00             19:00:00,700

jobd    16:00:00            17:00:00, 800

 

want to show with time as x-axis 

 

this woudl allow us to monitor which jobs running when e.g overlaps etc. and jobs on y axis with thickness of bar determined by size of amount_processed - higher amount thicket the bar.

 

How can this best be achieved in power bi?

 

Thansk

1 ACCEPTED SOLUTION
v-kkf-msft
Community Support
Community Support

Hi @po ,

 

Try to use Gannt chart by Microsoft, then set duration unit and date type.

 

image.png

image.png

 

If the problem is still not resolved, please provide detailed error information or the expected result you expect. Let me know immediately, looking forward to your reply.

Best Regards,
Winniz

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

6 REPLIES 6
v-kkf-msft
Community Support
Community Support

Hi @po ,

 

When the visual shows time, I think the height should be not determined by size of amount_processed. And you can try the following instead.

 

Gantt Chart viausl:

v-kkf-msft_0-1620968976987.png

Craydec Timelines visual:

image.png

 

If the problem is still not resolved, please provide detailed error information or the expected result you expect. Let me know immediately, looking forward to your reply.

Best Regards,
Winniz

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi,

 

Thanks for reply.

 

Do you have the sample .pbix file you are using with gantt chart?

 

Tried and whilst looks to give us what after not sure how can adjust scale to 2 hours and yours looks tidier than when have below.

 

Thanks

 

gantt_scale.JPG

v-kkf-msft
Community Support
Community Support

Hi @po ,

 

This is my PBIX file, I hope it is helpful.

 

Best Regards,
Winniz

Hi,

 

Thanks for reply.

 

Notice your gannt chart is the one by xviz.

 

Looking to do this with cust eith default visuals in teh desktop or custom visuals by Microsft.

 

Is it possible to have 2 hour time intervals in the custom gannt chart visual from microsft?

 

 

Thanks

v-kkf-msft
Community Support
Community Support

Hi @po ,

 

Try to use Gannt chart by Microsoft, then set duration unit and date type.

 

image.png

image.png

 

If the problem is still not resolved, please provide detailed error information or the expected result you expect. Let me know immediately, looking forward to your reply.

Best Regards,
Winniz

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Thanks for info

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors