Hi all,

Need some help for the following.

Below is a simple table.

My question is as follows: how can I calculate the AVERAGE of the TIME_TO_COMPLETE_1 values per day?

Thanks!

John

 

Knipsel.JPG

1 ACCEPTED SOLUTION

You can change the measure to be as follows:

 

 

AverageTimeConsumption =
VAR Days = INT ( AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) )
VAR HoursValue = ( AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) - Days ) * 24
VAR Hours = INT ( HoursValue )
VAR MinsValue = ( HoursValue - Hours ) * 60
VAR Mins = INT ( MinsValue )
VAR Seconds = ROUND ( ( MinsValue - Mins ) * 60, 0 )
RETURN
    IF (
        AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) <> BLANK (),
        FORMAT ( Days, "00" ) & ":"
        & FORMAT ( Hours, "00" ) & ":"
        & FORMAT ( Mins, "00" ) & ":"
        & FORMAT ( Seconds, "00" )
    )

 

 

 

Credit goes to Philip Treacy who wrote a clear article on this topic.

View solution in original post

5 REPLIES 5
Mohammad_Refaei
Solution Specialist
Solution Specialist

You need to use only a simple average formula if you have a calendar table.

Please check this sample file

Hi @Mohammad_Refaei,

I looked at your sample file, which is clear to me (I have a calender table).

Last question: the outcome of the measure is a decimal number, where I want to see TIME.

Any tip how to convert?

Thanks so far!

John

 

You can change the measure to be as follows:

 

 

AverageTimeConsumption =
VAR Days = INT ( AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) )
VAR HoursValue = ( AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) - Days ) * 24
VAR Hours = INT ( HoursValue )
VAR MinsValue = ( HoursValue - Hours ) * 60
VAR Mins = INT ( MinsValue )
VAR Seconds = ROUND ( ( MinsValue - Mins ) * 60, 0 )
RETURN
    IF (
        AVERAGEX ( 'Table', 'Table'[time_to_complete_1] ) <> BLANK (),
        FORMAT ( Days, "00" ) & ":"
        & FORMAT ( Hours, "00" ) & ":"
        & FORMAT ( Mins, "00" ) & ":"
        & FORMAT ( Seconds, "00" )
    )

 

 

 

Credit goes to Philip Treacy who wrote a clear article on this topic.

perfect, thanks @Mohammad_Refaei !

vanessafvg
Super User
Super User

Hi john

firstly do you have a date table?  I can see you have a datetime field, if you wanting to calculate per day its probably best to create new column with only the date values not the time values.  You also need a date table, this is to manage the continuity of the date.  you would join the date table to your table.  You could then plot at a day level the average (time_to_complete)

 

if you share sample data it would be easy to do a mockup but you have only provided a picture which is not possible to import into an example, you would need to provide text.





If I took the time to answer your question and I came up with a solution, please mark my post as a solution and /or give kudos freely for the effort 🙂 Thank you!

Proud to be a Super User!




Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors