Hi fellows,
When there is “ahead” progress (e.g. planned= 50%, actual= 80%), the difference (30%) must be shown with positive (+) sign. And when there is “behind” progress (e.g. planned= 80%, actual= 25%), the difference (55%) must be shown with negative (-) sign.
And
difference between (0-19% goes Green), (20-39% goes Yellow), and (40-100% goes Red).
Currently I am using "Cards with States by OKViz"
Hi @bix,
If you add "planned" to Target section and place "actual" to Measure section of this visual, the difference value will be automatically displayed with "+"/"-" depending on whether it is a positive or negative value. But, to set conditional color for variance based on specific value range (0-19% goes Green, 20-39% goes Yellow, and 40-100% goes Red) is not avaiable now. You could submit idea here.
Best regards,
Yuliana Gu
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
107 | |
99 | |
76 | |
64 | |
58 |
User | Count |
---|---|
148 | |
113 | |
97 | |
84 | |
67 |