Trying to calculate Days between 2 date columns. Both Columns have nulls or no values

There is Actual Start and Actual End Date. Both columns have null values as project is in progress or no given date. Keep getting errors on below. Any suggestions? Just trying to get a number value on the difference between these 2 columns. Thanks

 

Days Between = If('BI Projects'[Actual Start]=BLANK(),"",DATEDIFF('BI Projects'[Actual Start], 'BI Projects'[Actual End],DAY))

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

View solution in original post

3 REPLIES 3
ResearchDev
Helper II
Helper II

Thanks so much! Worked like magic!

tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

Thanks so much!

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.