Trying to calculate Days between 2 date columns. Both Columns have nulls or no values

There is Actual Start and Actual End Date. Both columns have null values as project is in progress or no given date. Keep getting errors on below. Any suggestions? Just trying to get a number value on the difference between these 2 columns. Thanks

 

Days Between = If('BI Projects'[Actual Start]=BLANK(),"",DATEDIFF('BI Projects'[Actual Start], 'BI Projects'[Actual End],DAY))

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

View solution in original post

3 REPLIES 3
ResearchDev
Helper II
Helper II

Thanks so much! Worked like magic!

tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

Thanks so much!

Helpful resources

Announcements
September Update

Check it Out!

Click here to learn more about the September 2022 updates!

Power BI Dev Camp Session 26

New Date - Check it Out!

Mark your calendars and join us on Thursday, October 6 at 11a PDT for a great session with Ted Pattison!

Top Solution Authors