Total COST by START MONTH, if the FINISH DATE is AFTER the START MONTH

With this problem, I am a bit overwhelmed with my little DAX knowledge and hope that someone here can give me a solution approach.

I do have the request from my colleagues to show the cost by month based on the start date but not finishing in that month.

I am looking for a measure that summarizes the cost on the StartDate month where the FinishDate is after the StartDate month

 

This is how the data look like

Typhoon74_0-1660808869349.png

 

The result should look like this

039 Image.png

 

Many thanks in advance

 

1 ACCEPTED SOLUTION
ryan_mayu
Super User
Super User

@Typhoon74 

1.PNG

pls see the attachment below





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




View solution in original post

3 REPLIES 3
ryan_mayu
Super User
Super User

@Typhoon74 

1.PNG

pls see the attachment below





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




Thank you @ryan_mayu it can be so easy when thinking the right way 😉

you are welcome





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!




Helpful resources

Announcements
Vote for T-Shirt Design

Power BI T-Shirt Design Challenge 2023

Vote for your favorite t-shirt design now through March 28.

March 2023 Update3

Power BI March 2023 Update

Find out more about the March 2023 update.

March Events 2023A

March 2023 Events

Find out more about the online and in person events happening in March!

Top Solution Authors