Timeline slicer - 8 days on Week 5 of 2016?

As the title says W5 of 2016 seems to have 8 days on timeline slicer, beginning from Jan 31st and ending at Feb 7th :8daysaweek.png

I really need each week to have only 7 days, W6 beginning at Feb 7th instead of 8th. Is there any way to change this? Anyone else having this problem?

 

Thanks!

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Impactful Individual
Impactful Individual

Re: Timeline slicer - 8 days on Week 5 of 2016?

@jluoma, thanks for reporting this issue. It is already been fixed in the 1.3.14 version Timeline chart. Please download it and try it again.  

View solution in original post

7 REPLIES 7
Highlighted

Re: Timeline slicer - 8 days on Week 5 of 2016?

What does the data in your table say?



* Matt is a Microsoft MVP (Power BI) and author of the Power BI Book Supercharge Power BI.
Highlighted
Regular Visitor

Re: Timeline slicer - 8 days on Week 5 of 2016?

Do you mean the source dataset or the table visualization? The source dataset (SSAS database) has a datetime field, which is used as Time on the timeline slicer. If W5 is chosen with the timeline slicer, the visualization shows values of days from Jan 31st to Feb 7th (I'd like it to be from Jan 31st to Feb 6th, beginning from sunday and ending on saturday). The weeks before W5 are fine, but W5 has this one extra day, which offsets all the weeks after W5 by one day.

Highlighted

Re: Timeline slicer - 8 days on Week 5 of 2016?


@jluoma wrote:

Do you mean the source dataset or the table visualization?


I mean what ever data is used to populate your slicer

 

sounds like a bug



* Matt is a Microsoft MVP (Power BI) and author of the Power BI Book Supercharge Power BI.
Highlighted
Regular Visitor

Re: Timeline slicer - 8 days on Week 5 of 2016?

Yes, the field used to populate the slicer is a field that is transformed into a Date-field in the query editor. Sound like a bug to me too 🙂

Highlighted
Microsoft
Microsoft

Re: Timeline slicer - 8 days on Week 5 of 2016?

@jluoma

 

The same behavior of Timeline slicer is reproduced in my test.  I will report this internally and would post back if there comes any update. Thanks for your feedback. 🙂

Highlighted
Impactful Individual
Impactful Individual

Re: Timeline slicer - 8 days on Week 5 of 2016?

@jluoma, thanks for reporting this issue. It is already been fixed in the 1.3.14 version Timeline chart. Please download it and try it again.  

View solution in original post

Highlighted
Regular Visitor

Re: Timeline slicer - 8 days on Week 5 of 2016?

I'm using version 1.3.17 and the same issue is back again in week 2017-12. The timeline selects 20 - 27 march. (and should select 20-26 march) I think it has to so with the daylight saving time (DST) (that occurs on 26th march in the Netherlands). Reinstalling of the custom visual did not work. The fist day of the week is set to monday. Result : week 1 till 11 everything OK, from week 12 problem in selecting the correct days. When first day of week is set to sunday, result : week 1-11 problem in selecting the correct days, and from week 12 OK

 

 Any help would be appriciated.

 

 

 

Helpful resources

Announcements

August Community Highlights

Check out a full recap of the month!

August 2020 CYST Challenge

Check out the winners of the recent 'Can You Solve These?' community challenge!

Experience what’s next for Power BI

Join us for an in-depth look at the new Power BI features and capabilities at the free Microsoft Business Applications Launch Event.

Top Solution Authors
Top Kudoed Authors