Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

Register now to learn Fabric in free live sessions led by the best Microsoft experts. From Apr 16 to May 9, in English and Spanish.

Reply
abernardez
Regular Visitor

Project Online custom report

Hi all,

 

We have created a planning in Project Online, our planning is for a long project with a lot of diferents tasks. Then we need to monitor the tasks in detail.

I have already conect with the data, and i can read the values of % and de %planned, but % completed is a temporal value in that moment i would like to record when someone upload the value of the % completed  to be able to graph how is going the project.

 

It is possible? 

 

 Thanks!

Anxo

 

1 REPLY 1
v-sihou-msft
Employee
Employee

@abernardez

 

I'm not sure if there's any column recording the "increment" amount of entire project uploaded by each individual user in Project Online datasets. If there's no such column at that detail level, it's not possible to achieve your goal. 

 

You may ask this question on ProjectOnline Forum:

https://social.technet.microsoft.com/Forums/projectserver/en-US/home?forum=projectonline

 

Regards,

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.