Non Working Days Calculation

Hi All My first post so be gentle!!! I have to determine is a transaction date is either "on time" or "late". The criteria to determine this is: On time = 5 days early of the request date, 0 days after the request date. Late = any date after the request date. What I need help with is how to discount non working days within the below formula: Del Status = if([Day Variation]>=0&&[Day Variation]<=5,"ON TIME", IF([Day Variation]<0,"LATE", "EARLY") Any help is greatly appreciated!

2 ACCEPTED SOLUTIONS

Accepted Solutions
Highlighted
Super User V
Super User V

Re: Non Working Days Calculation

Highlighted
Super User VI
Super User VI

Re: Non Working Days Calculation

A good approach for this is to make a Date table with an IsWorkingDay column based on your work week and then you can write a simple expression to count how many working days occur between two dates.  This video/article gives the details.

 

https://www.sqlbi.com/articles/counting-working-days-in-dax/

 

If this works for you, please mark it as the solution.  Kudos are appreciated too.  Please let me know if not.

Regards,

Pat





Did I answer your question? Please mark my post as a solution! Kudos are also appreciated!

Proud to be a Super User!




View solution in original post

6 REPLIES 6
Highlighted
Super User V
Super User V

Re: Non Working Days Calculation

Highlighted
Super User VI
Super User VI

Re: Non Working Days Calculation

A good approach for this is to make a Date table with an IsWorkingDay column based on your work week and then you can write a simple expression to count how many working days occur between two dates.  This video/article gives the details.

 

https://www.sqlbi.com/articles/counting-working-days-in-dax/

 

If this works for you, please mark it as the solution.  Kudos are appreciated too.  Please let me know if not.

Regards,

Pat





Did I answer your question? Please mark my post as a solution! Kudos are also appreciated!

Proud to be a Super User!




View solution in original post

Highlighted
Super User IX
Super User IX

Re: Non Working Days Calculation

@Ding_Dong43 , create a date calendar with the following column

Date = CALENDAR(date(2018,01,01), date(2021,12,31)) 
Work Day = if(WEEKDAY([Date],2)>=6,0,1) 
Work Date Cont = if([Work Day]=0,maxx(FILTER('Date',[Date]<EARLIER([Date]) && [Work Day]<> EARLIER([Work Day]) ),[Date]),[Date])
Work Date cont Rank = RANKX(ALL('Date'),[Work Date Cont],,ASC,Dense)

 

You can travel across Working days like

Plus 10 Days = var _max =maxx(ALLSELECTED('Date'),'Date'[Work Date cont Rank])
return CALCULATE(Min('Date'[Date]),filter(ALL('Date'),'Date'[Work Date Rank] =_max+10))



Did I answer your question? Mark my post as a solution! Appreciate your Kudos!!
Dashboard of My Blogs !! YouTube Channel !! Connect on Linkedin

Proud to be a Super User!

Highlighted
Regular Visitor

Re: Non Working Days Calculation

Hi Amit

 

Thanks so much for taking the time to reply.

 

Tried several ways with this, with varying results.

Ended up doing the following:

Del Status =
if([DeliveryWorkingDays]>0&&[DeliveryWorkingDays]<=1,"ON TIME",
IF([DeliveryWorkingDays]>1,"LATE", "EARLY"))

 

Seems to work... but not as elegant perhaps, it's all a learning curve!!!

Highlighted
Regular Visitor

Re: Non Working Days Calculation

Hi harshnathani

 

Thanks for the advice

Highlighted
Regular Visitor

Re: Non Working Days Calculation

Thanks for the help mohoneypat, appreciate it

Helpful resources

Announcements

August Community Highlights

Check out a full recap of the month!

August 2020 CYST Challenge

Check out the winners of the recent 'Can You Solve These?' community challenge!

Experience what’s next for Power BI

Join us for an in-depth look at the new Power BI features and capabilities at the free Microsoft Business Applications Launch Event.

Top Kudoed Authors