Hi,

 

I have the following DAX for Networkdays and the issue is that my calculation in Excel doesn't have Holidays and DAX forces the use of Holidays.

 

 

 

WorkingDaysMeasure = 
VAR AbStartDate = SELECTEDVALUE(SicknessAbsence[AbsenceStartDate])
VAR abEndDate = SELECTEDVALUE(SicknessAbsence[AbsenceEndDate])
RETURN
NETWORKDAYS(AbStartDate,abEndDate,1,'Bank Holidays')

 

Is there another way to calculate Netwrok Days in DAX  but without Holidays?

1 ACCEPTED SOLUTION
GJ217
Resolver III
Resolver III

I took off the 'Bank Holidays' and it worked.

View solution in original post

1 REPLY 1
GJ217
Resolver III
Resolver III

I took off the 'Bank Holidays' and it worked.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.