Making a risk report from MS Project Online - creating visuals

I am a new user and am trying to create a risk report on PowerBI using information about projects which has been imported from MS Project Online.

1. I want to calculate the number of risks per project and show this in a visual. I think I need to add an extra column in the underlying data tables using a fornula to calculate this. However, I'm unsure whether this should be created in the Risks table or the Projects table and what formula to use. Each Project has a unique ProjectID and this is the common key between tables. Each Risk also has a unique RiskID but multiple risks can be linked to each project and some have no risks attached at all.

2. I would then like to create a donut chart which shows the total number of projects available but split by whether or not they have any risks attached. I think I can use the information from step one and then when I know whether a project has a risk number of 0 or anything more, I should turn this in to a binary figure. However, I am unsure how to create a formula in the data tables to do so.

Any help would be much appreciated. 

1 ACCEPTED SOLUTION
v-jialluo-msft
Community Support
Community Support

Hi @Charday ,

 

Please follow these steps:

(1)Create a measure to calculate the number of risks per project.

 

Number of risks = CALCULATE(COUNT(Risk[ID]),FILTER(ALL(Risk),Risk[Project ID] = MAX(Project[ID])))

 

 

(2) Create a calculated column to determine whether the project is at risk

 

ISRISK = IF([Number of risks]>0,"RISK","NO RISK")

 

 

(3) Final output

vjialluomsft_0-1669616128532.png

 

 

Best Regards,

Gallen Luo

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

1 REPLY 1
v-jialluo-msft
Community Support
Community Support

Hi @Charday ,

 

Please follow these steps:

(1)Create a measure to calculate the number of risks per project.

 

Number of risks = CALCULATE(COUNT(Risk[ID]),FILTER(ALL(Risk),Risk[Project ID] = MAX(Project[ID])))

 

 

(2) Create a calculated column to determine whether the project is at risk

 

ISRISK = IF([Number of risks]>0,"RISK","NO RISK")

 

 

(3) Final output

vjialluomsft_0-1669616128532.png

 

 

Best Regards,

Gallen Luo

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Carousel_PBI_Wave1

2023 Release Wave 1 Plans

Power BI release plans for 2023 release wave 1 describes all new features releasing from April 2023 through September 2023.

Power BI Summit Carousel 2

Global Power BI Training

Make sure you register today for the Power BI Summit 2023. Don't miss all of the great sessions and speakers!

BizApps LATAM 2023

Business Application LATAM Summit 2023

Join the biggest FREE Business Applications Event in LATAM this February.

Power Platform Bootcamp

Global Power Platform Bootcamp

In this bootcamp we will deep-dive into Microsoft’s Power Platform stack with hands-on sessions and labs, delivered to you by experts and community leaders.