How to show % completion on Gantt chart

My % completion is showing 100% when it is actually 51% or more. When I set it to 50% or less, it shows 0%.

 

Please let me know how to fix this issue and show correct % completion on my visual.

 

Thank you.

 

Val

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @Val ,

 

I guess it is because you set the "Data type" as "Whole Number".

 

The way to fix it : Modeling  -> datatype: Decimal Number -> %

 

If still does not work, go to "Edit Queries" -> transform -> datatype: Decimal Number

 

 

Please choose as a solution if it helps.

View solution in original post

3 REPLIES 3
Anonymous
Not applicable

Hi @Val ,

 

I guess it is because you set the "Data type" as "Whole Number".

 

The way to fix it : Modeling  -> datatype: Decimal Number -> %

 

If still does not work, go to "Edit Queries" -> transform -> datatype: Decimal Number

 

 

Please choose as a solution if it helps.

Just wanted to point out that the " "Edit Queries" -> transform -> datatype: Decimal Number" fixed the issue.

 

Thanks.

 

Val

OMG tatasherry! It worked.

I spent all week trying to figure out this.

Thank you so much for the quick response.

 

Val

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.