Hello everyone. I was hoping someone could help please.

 

I have 4 columns in a table, each column is a separate field from the same query.

The columns as per the picture below, are QC Planned Start Date, Actual Start Date, Planned End Date and Actual End Date

Pricey79_0-1620913149186.png

How could I get it to show red or green depending on if the actual is before, or on the planned date please?

So for example:

Planned End is the 19th and Actual End is 21st, then red

Planned End is the 10th , Actual end 9th , then green

 

So two different formats, one for planned start and planned end, and one for actual start and actual end please.

Hope that makes sense.

 

Thank You in advance.

2 ACCEPTED SOLUTIONS
HashamNiaz
Solution Sage
Solution Sage

Hi !

You can create a column using following DAX to calculate if Planned End Date >= Actual End Date, you can do similar for Start date as well.

 

Planned End Date High = IF(Table[QC Planned End Date] >= Table[QC Actual End Date], 1, 0)

 

Now you can use this field in conditional formating, go to Format -> Conditional Formatting -> Background color -> On;

 

Colors4Colors4

 

You can adjust the Red & Green color based on your requirement.

 

Regards,

Hasham

 

View solution in original post

@HashamNiaz 

 

Works perfectly. Thank you so much

View solution in original post

2 REPLIES 2
HashamNiaz
Solution Sage
Solution Sage

Hi !

You can create a column using following DAX to calculate if Planned End Date >= Actual End Date, you can do similar for Start date as well.

 

Planned End Date High = IF(Table[QC Planned End Date] >= Table[QC Actual End Date], 1, 0)

 

Now you can use this field in conditional formating, go to Format -> Conditional Formatting -> Background color -> On;

 

Colors4Colors4

 

You can adjust the Red & Green color based on your requirement.

 

Regards,

Hasham

 

View solution in original post

@HashamNiaz 

 

Works perfectly. Thank you so much

View solution in original post

Helpful resources

Announcements
PBI_User Group Leader_768x460.jpg

Manage your user group events

Check out the News & Announcements to learn more.

MBAS on Demand

2021 Release Wave 2 Plan

Power Platform release plan for the 2021 release wave 2 describes all new features releasing from October 2021 through March 2022.

Get Ready for Power BI Dev Camp

Microsoft named a Leader in The Forrester Wave

Microsoft received the highest score of any vendor in both the strategy and current offering categories.

R2 (Green) 768 x 460px.png

Microsoft Dynamics 365 & Power Platform User Professionals

DynamicsCon is a FREE, 4 half-day virtual learning experience for 11,000+ Microsoft Business Application users and professionals.

Top Solution Authors
Top Kudoed Authors