Help needed visualizing Gantt/Timeline Chart

Hello, I'm looking to visualize a timeline for a project. My input table structure looks like this:

 

Project IDFunding ApprovedScope CompleteProject Started
Project 12/1/20192/20/20194/15/2019
Project 22/2/20193/2/20194/10/2019
Project 32/3/20193/3/20195/5/2019
Project 42/4/20192/15/20194/1/2019
Project 52/1/20193/10/2019

4/20/2019

 

 

The output I want is something like this:

 

image.png

 

Still a newbie when it comes to powerbi. Any help is appreciated.

 

Thank you!

1 ACCEPTED SOLUTION
v-lili6-msft
Community Support
Community Support

hi, @RustyNails 

There are three date fields in your dataset, if you could try this way:

In Edit Queries, Unpivot Funding Approved,Scope Complete,Project Started column

6.JPG

Then download the custom visual Timeline Chart

7.JPG

Best Regards,

Lin

 

 

Community Support Team _ Lin
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
v-lili6-msft
Community Support
Community Support

hi, @RustyNails 

There are three date fields in your dataset, if you could try this way:

In Edit Queries, Unpivot Funding Approved,Scope Complete,Project Started column

6.JPG

Then download the custom visual Timeline Chart

7.JPG

Best Regards,

Lin

 

 

Community Support Team _ Lin
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Edit: Never mind, Found it!! "Y Axis Label Length" under appearance. Thank you once again!

 

Thank you this worked! I just have to figure out how to make Project IDs show up fully on the Y axis. They cut off with like "Proj..." so its hard to tell if its Project 1, 2, 3 etc.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.