I am trying to get the dates of milestone completion to show up on my gantt chart using the Resource field. My data is structured as follows:
Table 1 'Improvements'
List of projects (1 per row) with corresponding project information
Table 2 'Actions'
List of actions (1 action per row) with corresponding deadline
Measure "Duration Action" = Action deadline - TODAY() - this results in the # of days until the deadline.
Measure "Next MS Date" = CALCULATE(MIN(Actions[Deadline]), 'Actions'[Deadline] >= TODAY())
The two tables are tied together (one to many) based on a project Id. I am using the gantt chart by putting Project Name from Table 1 in the Task field and "Duration Action" from Table 2 in the Duration field. What I want to show in the Resource field is "Next MS Date" so that it shows on the Gantt, but when I try to drag it over, the field won't accept it and Resource remains empty.
Is there any workaround to this?
Thanks
Hi @Anonymous,
I can add dates in the field Resource. So data type isn't the cause.
1. I think these two Measures should be Calculated columns. What are they exactly?
2. Which table is in the one side of the relationship?
3. Can you share a dummy sample please?
Best Regards,
Dale
I've made a dummy copy but how do I upload? I only see an option to upload photos and videos.
"Project Title" as the Task
"Duration Action2" as the Duration
"Start Date" is Today's date (I created a calculated column for this but it's not included in the dummy copy)
I already can do the above - I've included a snapshot of what that currently looks like. What I want to add is this:
"Next Milestone" to Legend
"Next MS Date" to Resources
that way, the bars are colored by the name of the next milestone and match what's in the table. Also the dates are displayed on each bar.
Hi @Anonymous,
You can upload your file to a cloud drive like Onedirve, GoogleDrive, then send me the share link. If you don't want to post here, you can send me a message via Messages. It's better to share here, then more people could give suggestions.
Best Regards,
Dale
1. the Duration Action measure is the amount of days from today until the action deadline.
2. The Project table has 1 project per line and the Actions table has one action per line. One project can have several actions, so actions is the "many" and projects is the "one".
3. I can upload a dummy copy, but the source file is from a sharepoint site. Will that cause issues with you playing with the data?
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
113 | |
97 | |
85 | |
70 | |
61 |
User | Count |
---|---|
151 | |
121 | |
104 | |
87 | |
67 |