Hi,
I tried to create a gauge visual but it is displaying the sum of my budget column and not the actual budget. Any ideas on how to fix this? The budget maximum should be 1.5m.
Solved! Go to Solution.
Hi @PeterVE
For Gauge visual , you can only put fields with Whole number type in it . In Target value , the value for field is impossible to display classified .So when you put field “Budget” in Target value , the displayed data is not your actual data in the master table, but aggregated calculations .
My suggestion is adding a slicer with “Date” from master table. And choose sum for “Budget” in Target value .
I have attached my pbix file ,you can refer to it .
Best Regards
Community Support Team _ Ailsa Tao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @PeterVE
For Gauge visual , you can only put fields with Whole number type in it . In Target value , the value for field is impossible to display classified .So when you put field “Budget” in Target value , the displayed data is not your actual data in the master table, but aggregated calculations .
My suggestion is adding a slicer with “Date” from master table. And choose sum for “Budget” in Target value .
I have attached my pbix file ,you can refer to it .
Best Regards
Community Support Team _ Ailsa Tao
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
@PeterVE , check what all column you have given, Please share those
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
110 | |
95 | |
76 | |
65 | |
51 |
User | Count |
---|---|
146 | |
109 | |
106 | |
88 | |
61 |