Gantt chart showing real and planned finish date

Dear all,

 

I'm trying to creat a Gantt chart based on a list of tasks and dates. I've been able to show it using Gantt Chart by MAQ Software nevertheless, I'm not able to show the difference between the Planned Finish Date and the Real Finish Date. For example:

 

Task Name - Task 1

Tast Start Date - 15/07/2018

Task Finish Date - 30/07/2018

Task Real Finish Date - 05/08/2018

 

How could I show this? 

Thank you in advance!

2 REPLIES 2
siqsi
Regular Visitor

Dear all,

 

I'm trying to creat a Gantt chart based on a list of tasks and dates. I've been able to show it using Gantt Chart by MAQ Software nevertheless, I'm not able to show the difference between the Planned Finish Date and the Real Finish Date. For example:

 

Task Name - Task 1

Tast Start Date - 15/07/2018

Task Finish Date - 30/07/2018

Task Real Finish Date - 05/08/2018

 

How could I show this? 

Thank you in advance!

v-juanli-msft
Community Support
Community Support

Hi @siqsi

Per your requirement, i would recommend you to consider Gantt Chart which is similar to Gantt Chart by MAQ Software and also show the difference between real completed time and planned completed time.

Reference here

https://www.mpug.com/articles/how-to-create-an-amazing-gantt-chart-in-power-bi/

http://blog.pragmaticworks.com/power-bi-custom-visuals-gantt

 

Best reagrds

Maggie

Helpful resources

Announcements
April AMA free

Microsoft Fabric AMA Livestream

Join us Tuesday, April 09, 9:00 – 10:00 AM PST for a live, expert-led Q&A session on all things Microsoft Fabric!

March Fabric Community Update

Fabric Community Update - March 2024

Find out what's new and trending in the Fabric Community.