Gijs Regular Visitor
Regular Visitor

Gantt chart by maq software multiple phases on 1 row?

Hi All,

 

I am trying to create a Gantt chart which encompases multiple smaller projects. All these projects have approx 3/4 phases.

 

I first used the normal Gantt chart options and was able by grouping to get the phases as multiple colors next to eachother. The problem with the normal Gantt chart is however for me that you cannot add more information than just a title next to the row. (I would like to have title, person responsible, priority etc.) next to the visuals of the phases.

 

I started to look into the Gantt chart by Maq software, this one does help me with adding more information next to the bars. I have issues however with the grouping of tasks. When I use the hierarchy lay-out I get the different tasks grouped by project, but below eachother rather than next to eachother. Is there a way with the Gantt Chart by Maq Software to show phases next to eachoter?

 

Regards.

Gijs

1 ACCEPTED SOLUTION

Accepted Solutions
MAQSupport Member
Member

Re: Gantt chart by maq software multiple phases on 1 row?

Hello @Gijs 

 

Currently, Gantt Chart by MAQ Software supports showing tasks under same category one below other in hierarchy layout.

 

We have added your request to show these tasks next to each other to our backlog

We will notify you on this thread when we upgrade our visual with this feature.

 

Thanks.

View solution in original post

2 REPLIES 2
Community Support Team
Community Support Team

Re: Gantt chart by maq software multiple phases on 1 row?

@Gijs ,

 

You may take a look at the following post.

https://community.powerbi.com/t5/Desktop/Gantt-chart-by-MAQ-Software-Help/m-p/669764#M322246

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
MAQSupport Member
Member

Re: Gantt chart by maq software multiple phases on 1 row?

Hello @Gijs 

 

Currently, Gantt Chart by MAQ Software supports showing tasks under same category one below other in hierarchy layout.

 

We have added your request to show these tasks next to each other to our backlog

We will notify you on this thread when we upgrade our visual with this feature.

 

Thanks.

View solution in original post

Helpful resources

Announcements
Can You Solve These Challenge

Challenge: Can You Solve These?

Find out how to participate in the first Power BI 'Can You Solve These?' challenge.

New Badges

Incoming: New and Improved Badges

Exciting news: We've given our badges an overhaul and added brand news ones.

Ask Amir Anything

Exclusive LIVE Community Event No. 2 – Ask Amir Anything

Next in our Triple A series: Ask Amir Netz questions about the latest updates, features and future.

Analytics in Azure virtual event

Analytics in Azure virtual event

Experience a limitless analytics service built to ingest, prep, manage, and serve data for immediate use in Power BI.

Users Online
Currently online: 285 members 2,605 guests
Please welcome our newest community members: