Gantt chart adjusted start date measure in Start date of Gantt chart not working

HI, 

I creating booking gantt that is used for viewing what days are already booked and which ones are free. Problem is that when I select date range in calendar filter, some bookings start before my minimal calendar date, so I must adjust start date in gantt to minimal calendar date, or gantt show dates before selected calendar date. I created measure for setting start date, but gantt start field is not accepting measure date as start date? Advise please, thanks

 

2017-06-22_10-49-23.jpg

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Microsoft
Microsoft

Re: Gantt chart adjusted start date measure in Start date of Gantt chart not working

Hi @tomislav1975,

 

In a Gantt chart, it is not available to add a measure into start date field.

 

In your scenario, you said the start date of Gantt chart was not filtered by the selected date from a slicer, right? Did you add date column from a separate calendar table into slicer, rather than the date column included in data table? If that is the case, please create a relationship between calendar table and data table based on date column.

 

Best regards,
Yuliana Gu

Community Support Team _ Yuliana Gu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

2 REPLIES 2
Highlighted
Microsoft
Microsoft

Re: Gantt chart adjusted start date measure in Start date of Gantt chart not working

Hi @tomislav1975,

 

In a Gantt chart, it is not available to add a measure into start date field.

 

In your scenario, you said the start date of Gantt chart was not filtered by the selected date from a slicer, right? Did you add date column from a separate calendar table into slicer, rather than the date column included in data table? If that is the case, please create a relationship between calendar table and data table based on date column.

 

Best regards,
Yuliana Gu

Community Support Team _ Yuliana Gu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

Highlighted
Helper V
Helper V

Re: Gantt chart adjusted start date measure in Start date of Gantt chart not working

You are not 100% on the spot, but your answer helped me to create somethig I can use. Thank you very much 🙂

Helpful resources

Announcements
Community Conference

Power Platform Community Conference

Find your favorite faces from the community presenting at the Power Platform Community Conference!

Upcoming Events

Experience what’s next for Power BI

See the latest Power BI innovations, updates, and demos from the Microsoft Business Applications Launch Event.

secondImage

Power Platform 2020 release wave 2 plan

Features releasing from October 2020 through March 2021

Get Ready for Power BI Dev Camp

Get Ready for Power BI Dev Camp

Mark your calendars and join us for our next Power BI Dev Camp!.

Top Solution Authors