Gantt chart - Cannot Add a Duration

Hi,

 

I have a Gantt Chart all set up like a time line showing me hours in a day (duration unit set to minutes in general settings), using timestamp (date/time) as start and end.  Everything is working perfectly except I cannot add a duration.  When I try to add a data field to the duration in the visual menu nothing happens, it won't stick.

 

The duration is in minutes.  I've tried transforming it to a duration, tired a new calculated column (End-Start), tried converting that to minutes, hours, days.  Nothing seems to work!  Am I missing something?

1 ACCEPTED SOLUTION

@pedanticpad 

I cannot enter Endtime and Duration field at the same time, try only enter column in to duration only.


Paul Zheng _ Community Support Team
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

5 REPLIES 5
Pragati11
Super User III
Super User III

Hi @pedanticpad ,

 

Please share some screenshots around what you are trying to do here.

It's hard to understand what you are trying to achieve using Gantt chart. Also, add some sample data so that we can try to replicate at our end.

 

Thanks,

Pragati





If this helps, Appreciate a KUDOS!
Did I answer your question? Mark my post as a solution!


Proud to be a Super User!




Sorry.  I thought I made sense when I wrote that.  See screenshot below, absolutely no field will populate in the Duration field.  No matter what I drag and drop it will not enter this field.  I though it something to do with my duration measure but no field at all will go into the Duration field in the settings.  Has anyone come accross this before?

 

image.png

@pedanticpad 

I cannot enter Endtime and Duration field at the same time, try only enter column in to duration only.


Paul Zheng _ Community Support Team
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

@

 

Hi @pedanticpad ,

 

Refer following link to see what DURATION value is epected in this Gantt chart. It looks more like that you have to create a new column with CALENDAR duration.

https://www.senseiprojectsolutions.com/2018/03/23/creating-calendar-duration-for-use-with-the-gantt-...

 

Thanks,

Pragati





If this helps, Appreciate a KUDOS!
Did I answer your question? Mark my post as a solution!


Proud to be a Super User!




Helpful resources

Announcements
PBI User Groups

Welcome to the User Group Public Preview

Check out new user group experience and if you are a leader please create your group!

MBAS on Demand

Microsoft Business Applications Summit sessions

On-demand access to all the great content presented by the product teams and community members! #MSBizAppsSummit #CommunityRocks

MBAS Attendee Badge

Claim Your Badge & Digital Swag!

Check out how to claim yours today!

secondImage

Are You Ready?

Test your skills now with the Cloud Skills Challenge.

Top Solution Authors