Hi,
I'm using the basic Gantt chart visualiser. I want to add slicer/check box where I can alternate between two set of dates (baseline dates and current dates) on the same window.
Can this be done on Power BI and how?
Ahmed K.
Solved! Go to Solution.
Hi @ahmedKalbani,
One way of doing this is with buttons and bookmarks.
Create 2 different Gantt charts and 2 bookmarks for the same page, with each bookmark showing a different Gantt chart. Then assign buttons to theses bookmarks to create the effect that they filter the chart.
Here's a reference.
Br,
T
Hi @ahmedKalbani,
One way of doing this is with buttons and bookmarks.
Create 2 different Gantt charts and 2 bookmarks for the same page, with each bookmark showing a different Gantt chart. Then assign buttons to theses bookmarks to create the effect that they filter the chart.
Here's a reference.
Br,
T
Thanks. that was the direction I needed.
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
111 | |
94 | |
83 | |
66 | |
59 |
User | Count |
---|---|
151 | |
121 | |
104 | |
87 | |
67 |