The Gannt chart looks to be perfect for a use case for me except, it doesn't seem to show 0 duration tasks (milestones) on the timeline? Is there a way around this?
Hi @nogi,
It's hard to show value "0". If you have resource in the field, you can have a label as milestones. How about this?
Best Regards!
Dale
I understand and why i've suggested that for milestones (0 day tasks), show a diamond or something. Haven't tried using a diamond character as a resource name though.
On a slightly different note, how do you update the visualisation? I noticed that the version on github is a few ahead of what is in the app store. But the github is only source files rather than the compiled visualisation.
Hi @nogi,
If you want to update the visualization, you can update the source table. If you want to update the visualization itself, you can import the visual from the Store again.
Best Regards!
Dale
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
111 | |
97 | |
80 | |
69 | |
59 |
User | Count |
---|---|
150 | |
119 | |
104 | |
87 | |
67 |