Find Earliest Date in baseline project

Hi All

 

Scratching my brain on this for a while now;

 

I have 2 projects, baseline and Current (6 months update of Baseline)

6 months into the project the Actual Cost sit at $30 MIllion.

I would like to create a measure that gives me the DATE where the Baseline would have achieved $30 Million.

In short; the earliest date in Baseline where the planned cost hits $30 M.

 

I am trying to figure out where the current project stands compared to Baseline.

 

Please help

1 ACCEPTED SOLUTION

@Anonymous,

 

You may research the code generated by Quick measure Running total.

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

3 REPLIES 3
Greg_Deckler
Super User
Super User

Need sample data...Please see this post regarding How to Get Your Question Answered Quickly: https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490

 

But, in general you could create a date table either actual or in a measure that has a running total cost column in it and then just filter for the MIN date that is over $30M.


@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...
Anonymous
Not applicable

 

Cumulative Actual is $4,027,910 (CURRENT)

Want to create a measure that tells me the date when the BASELINE achieves $4,027,910

 

Thanks for helping

 

 

DATA:

 

proj_idproj_short_nameBase and Currenttarget_start_datetarget_end_dateCumulative Budgeted(Measure)**bleep** Actual(Measure)
418HUB-BASEBaseline10/16/2017 0:0010/17/2017 0:00$326,000 
418HUB-BASEBaseline11/30/2017 0:0012/7/2017 0:00$88,240 
418HUB-BASEBaseline12/8/2017 0:0012/8/2017 0:00$11,724 
418HUB-BASEBaseline12/8/2017 0:0012/18/2017 0:00$132,360 
468HUB-JUN18Current12/14/2017 0:0012/19/2017 0:00$0$79,380
418HUB-BASEBaseline12/11/2017 0:0012/26/2017 0:00$117,240 
418HUB-BASEBaseline12/19/2017 0:0012/26/2017 0:00$2,538,228 
418HUB-BASEBaseline12/19/2017 0:0012/28/2017 0:00$88,240 
418HUB-BASEBaseline12/19/2017 0:0012/29/2017 0:00$110,300 
418HUB-BASEBaseline12/26/2017 0:0012/29/2017 0:00$66,470 
468HUB-JUN18Current12/18/2017 0:0012/29/2017 0:00$0$119,130
418HUB-BASEBaseline12/29/2017 0:001/5/2018 0:00$88,240 
418HUB-BASEBaseline12/19/2017 0:001/8/2018 0:00$134,480 
418HUB-BASEBaseline12/29/2017 0:001/8/2018 0:00$53,792 
468HUB-JUN18Current1/3/2018 0:001/8/2018 0:00$0$79,475
468HUB-JUN18Current1/5/2018 0:001/8/2018 0:00$0$39,725
418HUB-BASEBaseline1/3/2018 0:001/9/2018 0:00$110,300 
468HUB-JUN18Current1/4/2018 0:001/9/2018 0:00$0$79,420
418HUB-BASEBaseline12/19/2017 0:001/10/2018 0:00$175,860 
418HUB-BASEBaseline1/8/2018 0:001/15/2018 0:00$99,705 
418HUB-BASEBaseline1/8/2018 0:001/16/2018 0:00$110,300 
418HUB-BASEBaseline1/15/2018 0:001/17/2018 0:00$66,470 
418HUB-BASEBaseline1/12/2018 0:001/19/2018 0:00$110,300 
468HUB-JUN18Current1/2/2018 0:001/22/2018 0:00$0########
418HUB-BASEBaseline1/18/2018 0:001/23/2018 0:00$88,240 
468HUB-JUN18Current1/22/2018 0:001/23/2018 0:00$0$39,680
418HUB-BASEBaseline1/9/2018 0:001/25/2018 0:00$134,480 
418HUB-BASEBaseline1/17/2018 0:001/25/2018 0:00$67,240 
418HUB-BASEBaseline1/22/2018 0:001/29/2018 0:00$110,300 
418HUB-BASEBaseline1/25/2018 0:001/30/2018 0:00$88,240 
468HUB-JUN18Current1/29/2018 0:001/30/2018 0:00$0$39,680
418HUB-BASEBaseline1/30/2018 0:002/1/2018 0:00$44,120 
468HUB-JUN18Current1/26/2018 0:002/1/2018 0:00$0$897,812
418HUB-BASEBaseline1/25/2018 0:002/2/2018 0:00$94,136 
418HUB-BASEBaseline2/1/2018 0:002/2/2018 0:00$61,632 
468HUB-JUN18Current1/26/2018 0:002/2/2018 0:00$0$99,294
468HUB-JUN18Current1/26/2018 0:002/5/2018 0:00$0$99,264
418HUB-BASEBaseline2/2/2018 0:002/8/2018 0:00$19,605 
418HUB-BASEBaseline2/5/2018 0:002/8/2018 0:00$61,632 
418HUB-BASEBaseline2/1/2018 0:002/9/2018 0:00$110,300 
418HUB-BASEBaseline2/2/2018 0:002/12/2018 0:00$110,300 

@Anonymous,

 

You may research the code generated by Quick measure Running total.

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.