Hello,

I need to forecast work hours distributing the hour through the duration day.

I will use an example to be more clear.

I want to know how many hours per day I will need to work. 

How I create a table that looks like the result?

 

 

Table1:

EtienneB1_0-1596760010424.png

 

Table 2:

EtienneB1_1-1596760056597.png


Result:

 

EtienneB1_2-1596760097446.png

 

Please Help I have been stuck here for weeks

1 ACCEPTED SOLUTION
Icey
Community Support
Community Support

Hi @EtienneB1 ,

 

How about create a calculated table like so:

Crossjoin Table =
SUMMARIZE (
    FILTER (
        ADDCOLUMNS (
            CROSSJOIN ( CALENDARAUTO (), 'Table 1', 'Table 2' ),
            "enddate", [Start Date]
                + CALCULATE (
                    SUM ( 'Table 2'[Duration(days)] ) - 1,
                    FILTER (
                        ALL ( 'Table 2' ),
                        'Table 2'[Process Name] <= EARLIER ( 'Table 2'[Process Name] )
                    )
                ),
            "Hours", [Qty] * [Time per Unit(hours)] / [Duration(days)]
        ),
        VAR StartDate_ = [enddate] - [Duration(days)] + 1
        RETURN
            [Date] <= [enddate]
            && [Date] >= StartDate_
    ),
    [Date],
    [Id],
    [Process Name],
    [Hours]
)

crossjoin.PNG

 

For more details, please check the attached .pbix file.

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

5 REPLIES 5
Icey
Community Support
Community Support

Hi @EtienneB1 ,

 

Perhaps this is more helpful to your understanding:

 

My understanding is this:

 

You want to calculate the results of “Qty*Time Per Unit/Duration”.

 

If my understanding is right, try this:

 

1. Create a calculated column which is to calculate the duration of progress1 and progress2.

duration1 =
CALCULATE (
    SUM ( 'Table 2'[Duration(days)] ),
    FILTER (
        ALL ( 'Table 2' ),
        'Table 2'[Process Name] <= EARLIER ( 'Table 2'[Process Name] )
    )
)

duration1.png

 

2. Create a new table under Modeling.

Table 3 = 
VAR mycalendar =
    CALENDARAUTO ()
VAR table1 =
    ADDCOLUMNS (
        CROSSJOIN ( 'Table 1', 'Table 2', mycalendar ),
        "EndDate", 'Table 1'[Start Date] + 'Table 2'[duration1]
    )
VAR table2 =
    ADDCOLUMNS ( table1, "StartDate1", [EndDate] - 'Table 2'[Duration(days)] )
VAR table3 =
    ADDCOLUMNS (
        FILTER ( table2, [StartDate1] <= [Date] && [EndDate] >= [Date] ),
        "Hours", [Qty] * [Time per Unit(hours)] / [Duration(days)]
    )
RETURN
    SUMMARIZE (
        ADDCOLUMNS (
            table3,
            "Hours1", [Qty] & "*" & [Time per Unit(hours)] & "/" & [Duration(days)]
        ),
        [Date],
        [Id],
        [Process Name],
        [Hours1],
        [Hours]
    )

table3-1.png

 

You can check more details from here.

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Icey
Community Support
Community Support

Hi @EtienneB1 ,

 

How about create a calculated table like so:

Crossjoin Table =
SUMMARIZE (
    FILTER (
        ADDCOLUMNS (
            CROSSJOIN ( CALENDARAUTO (), 'Table 1', 'Table 2' ),
            "enddate", [Start Date]
                + CALCULATE (
                    SUM ( 'Table 2'[Duration(days)] ) - 1,
                    FILTER (
                        ALL ( 'Table 2' ),
                        'Table 2'[Process Name] <= EARLIER ( 'Table 2'[Process Name] )
                    )
                ),
            "Hours", [Qty] * [Time per Unit(hours)] / [Duration(days)]
        ),
        VAR StartDate_ = [enddate] - [Duration(days)] + 1
        RETURN
            [Date] <= [enddate]
            && [Date] >= StartDate_
    ),
    [Date],
    [Id],
    [Process Name],
    [Hours]
)

crossjoin.PNG

 

For more details, please check the attached .pbix file.

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Thank you so much for your help. 
One more thing, If I have IDs that has different workflow, What I mean that doesn't do all the processes maybe skip one or few. 
How I can do it?

Icey
Community Support
Community Support

Hi @EtienneB1 ,

 

I don't quite understand the scenario you mentioned. Please give me a specific example to help me better understand your requirements.

 

 

Best Regards,

Icey

 

 

amitchandak
Super User
Super User

@EtienneB1 , You can use crosstable with addcolumns, summarize, summarizecolumns

 

example

addcolumns(crorsstable(Table1, Table2), "Hours" , divide([Qty]*[Time per unit(Hour)],[Duration]))

Helpful resources

Announcements
April AMA free

Microsoft Fabric AMA Livestream

Join us Tuesday, April 09, 9:00 – 10:00 AM PST for a live, expert-led Q&A session on all things Microsoft Fabric!

March Fabric Community Update

Fabric Community Update - March 2024

Find out what's new and trending in the Fabric Community.