Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

Register now to learn Fabric in free live sessions led by the best Microsoft experts. From Apr 16 to May 9, in English and Spanish.

Reply
Anonymous
Not applicable

Distribute date ranges into groups automatically

Hello community folks!

 

I am trying to break project date ranges into 3 equal groups (where possible)  I have a list of all dates each project was worked, and want to automatically show which 3rd a date falls into.   See below

 

Project 17/4/20191
Project 17/5/20191
Project 17/6/20192
Project 17/7/20192
Project 17/8/20193
Project 17/9/20193
Project 28/10/20191
Project 28/11/20192
Project 35/4/20191
Project 35/5/20192
Project 35/6/20193

 

I have looked up Rank functions, etc, but am finding nothing where i can set the max number at 3.  Can anyone help me with this?

1 ACCEPTED SOLUTION

Hi  @Anonymous ,

 

First create a column as below:

Rank = RANKX(FILTER('Table','Table'[Project #]=EARLIER('Table'[Project #])),'Table'[Dates worked],,ASC)

Then create a measure as below:

Thirds = 
var _max=MAXX(FILTER(ALL('Table'),'Table'[Project #]=MAX('Table'[Project #])),'Table'[Rank])
var _count=CALCULATE(COUNT('Table'[Project #]),FILTER(ALL('Table'),'Table'[Project #]=MAX('Table'[Project #])))
Return
IF(_max<=3,MAX('Table'[Rank]),DIVIDE(MAX('Table'[Rank]),_count/3))

And you will see:

1.png

For the related .pbix file,pls see attached.

 

Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!

View solution in original post

11 REPLIES 11
pranit828
Community Champion
Community Champion

Hi @Anonymous 

I wouls use MOD in ths case.

Lets say you have the output of your rank function in 

Var _rank = RANK(......)

Return MOD(_rank,3)+1

 

This will give you the output only as 1, 2 and 3





PBI_SuperUser_Rank@1x.png


Hope it resolves your issue? 
Did I answer your question? Mark my post as a solution!

Appreciate your Kudos, Press the thumbs up button!!
Linkedin Profile
Anonymous
Not applicable

@pranit828   I'm sorry, I'm not following. Can you explain in more detail please? 

HI @Anonymous 

 

rank Measure = 

var _rank = RANKX( 'Table','Table'[Date],,ASC)
return MOD(_rank,3)+1




PBI_SuperUser_Rank@1x.png


Hope it resolves your issue? 
Did I answer your question? Mark my post as a solution!

Appreciate your Kudos, Press the thumbs up button!!
Linkedin Profile
Anonymous
Not applicable

@pranit828  im sorry to say that did not work.

 

With a live example, this is the result of your formula 

Project #Dates worked 
Project 1Friday, June 26, 20202
Project 1Saturday, June 27, 20201
Project 1Sunday, June 28, 20201
Project 1Monday, June 29, 20201
Project 1Tuesday, June 30, 20203
Project 1Wednesday, July 1, 20201
Project 1Thursday, July 2, 20201
Project 1Friday, July 3, 20202
Project 1Saturday, July 4, 20202
Project 1Sunday, July 5, 20201
Project 1Monday, July 6, 20203
Project 1Tuesday, July 7, 20202
Project 1Wednesday, July 8, 20203
Project 1Thursday, July 9, 20201
Project 1Friday, July 10, 20202
Project 1Saturday, July 11, 20201
Project 1Sunday, July 12, 20201
Project 1Monday, July 13, 20201
Project 1Tuesday, July 14, 20203
Project 1Wednesday, July 15, 20201
Project 1Thursday, July 16, 20201
Project 1Friday, July 17, 20203
Project 1Saturday, July 18, 20201
Project 1Sunday, July 19, 20201
Project 1Monday, July 20, 20201
Project 1Tuesday, July 21, 20201
Project 1Wednesday, July 22, 20203
Project 1Thursday, July 23, 20203
Project 1Friday, July 24, 20202
Project 1Saturday, July 25, 20203
Project 1Sunday, July 26, 20203
Project 1Monday, July 27, 20203

 

the result im looking for is below

Project #Dates worked 
Project 1Friday, June 26, 20201
Project 1Saturday, June 27, 20201
Project 1Sunday, June 28, 20201
Project 1Monday, June 29, 20201
Project 1Tuesday, June 30, 20201
Project 1Wednesday, July 1, 20201
Project 1Thursday, July 2, 20201
Project 1Friday, July 3, 20201
Project 1Saturday, July 4, 20201
Project 1Sunday, July 5, 20201
Project 1Monday, July 6, 20201
Project 1Tuesday, July 7, 20202
Project 1Wednesday, July 8, 20202
Project 1Thursday, July 9, 20202
Project 1Friday, July 10, 20202
Project 1Saturday, July 11, 20202
Project 1Sunday, July 12, 20202
Project 1Monday, July 13, 20202
Project 1Tuesday, July 14, 20202
Project 1Wednesday, July 15, 20202
Project 1Thursday, July 16, 20202
Project 1Friday, July 17, 20202
Project 1Saturday, July 18, 20203
Project 1Sunday, July 19, 20203
Project 1Monday, July 20, 20203
Project 1Tuesday, July 21, 20203
Project 1Wednesday, July 22, 20203
Project 1Thursday, July 23, 20203
Project 1Friday, July 24, 20203
Project 1Saturday, July 25, 20203
Project 1Sunday, July 26, 20203
Project 1Monday, July 27, 20203

 

Im trying to break the Projects duration into 3 parts... in chronological order.   So in the case above, the first 11 dates would be "1", the middle "2", and the latter "3"

Hi @Anonymous 

 

_number = 
var _cnt = rankx(allselected(Table1),CALCULATE ( MAX (Table1[Dates worked])),,ASC)
var _max = CALCULATE(COUNTROWS(Table1),ALLEXCEPT(table1,Table1[Project #]))
var _d3 = _max/3
return CEILING(_cnt/_d3,1)




PBI_SuperUser_Rank@1x.png


Hope it resolves your issue? 
Did I answer your question? Mark my post as a solution!

Appreciate your Kudos, Press the thumbs up button!!
Linkedin Profile
Anonymous
Not applicable

@pranit828 

 

So as a measure, it doesn't seem to stop at 3.  I see values up into the hundreds.

 

because of the insight im looking to get, the best solution for this would be a calculated column..however when i add the formula in for my new column I get the error "A circular dependency was detected: Table1[Column]."

 

any thoughts?

 

Hi @Anonymous 

According to your sample my previous reply answers your question.

 

Probably you should put more time in making a good sample of your data when ask so that you get to the point reply.

 Try the below as a measure, column is preferred when there is a calculation done for each row.

 

_number = 
var _cnt = rankx(allselected(Table1),CALCULATE ( MAX (Table1[Dates worked]), allexcept(table1, table1[Project #])),,ASC)
var _max = CALCULATE(COUNTROWS(Table1),ALLEXCEPT(table1,Table1[Project #]))
var _d3 = _max/3
return CEILING(_cnt/_d3,1)

 

 





PBI_SuperUser_Rank@1x.png


Hope it resolves your issue? 
Did I answer your question? Mark my post as a solution!

Appreciate your Kudos, Press the thumbs up button!!
Linkedin Profile
Anonymous
Not applicable

My apologies that my request was unclear.  I don't use the forums often to request help, so forgive me for thinking I had explained what i was looking for thoroughly enough.

 

I have tried your measure, and its actually gotten worse in the number return.  

 

I shall try to explain this more in depth.

 

The need:  To break down a Projects duration (start to finish) into thirds.  Identify which dates fall into which 3rd of each project.   Durations can be anywhere from 1 day to hundreds of days long. We have a table with thousands of projects of varying durations.  I have already created a table that shows the Project Number and each individual date the project was active.  shown here

 

Example Table:

Project #Dates worked
Project 17/4/2019
Project 17/5/2019
Project 17/6/2019
Project 17/7/2019
Project 17/8/2019
Project 17/9/2019
Project 28/10/2019
Project 28/11/2019
Project 35/4/2019
Project 35/5/2019
Project 35/6/2019

 

 

The request:  Can anyone help me create a Calculated Column, either in DAX or in Power Query, to label each row as either the first, middle or latter third of a project.  The result would look like below

 

Example Table 2: Desired Outcome

Project #Dates workedThirds
Project 17/4/20191
Project 17/5/20191
Project 17/6/20192
Project 17/7/20192
Project 17/8/20193
Project 17/9/20193
Project 28/10/20191
Project 28/11/20192
Project 35/4/20191
Project 35/5/20192
Project 35/6/20193

 

 

I hope this explanation is clearer than my original ask.

Hi  @Anonymous ,

 

First create a column as below:

Rank = RANKX(FILTER('Table','Table'[Project #]=EARLIER('Table'[Project #])),'Table'[Dates worked],,ASC)

Then create a measure as below:

Thirds = 
var _max=MAXX(FILTER(ALL('Table'),'Table'[Project #]=MAX('Table'[Project #])),'Table'[Rank])
var _count=CALCULATE(COUNT('Table'[Project #]),FILTER(ALL('Table'),'Table'[Project #]=MAX('Table'[Project #])))
Return
IF(_max<=3,MAX('Table'[Rank]),DIVIDE(MAX('Table'[Rank]),_count/3))

And you will see:

1.png

For the related .pbix file,pls see attached.

 

Best Regards,
Kelly
Did I answer your question? Mark my post as a solution!
Greg_Deckler
Super User
Super User

@Anonymous Sorry, not following this completely. Are you showing us sample source data, expected output, both? If this is sample source data can you post expected output and the logic behind how you want the transformation to happen? 

 

Are you simply looking for the MAX number per project in the last column? You could do that via Lookup Min/Max - https://community.powerbi.com/t5/Quick-Measures-Gallery/Lookup-Min-Max/m-p/985814#M434

 

In your case, 

Measure =
  VAR __Project = MAX([Project])
  VAR __MaxStatus = MAXX(FILTER('Table',[Project]=__Project),[Status])
RETURN
  __MaxStatus

@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...
Anonymous
Not applicable

Sorry about that @Greg_Deckler   I showed the final output i was going for.

 

I have a list of projects and all the dates those projects were worked on. shown here.

Project #Dates worked
Project 17/4/2019
Project 17/5/2019
Project 17/6/2019
Project 17/7/2019
Project 17/8/2019
Project 17/9/2019
Project 28/10/2019
Project 28/11/2019
Project 35/4/2019
Project 35/5/2019
Project 35/6/2019

 

What i need to do is break each set of dates, by project, up to a max of 3 groups.(essentially splitting the project duration into 3rds)   The end result would look like this.

Project #Dates worked 
Project 17/4/20191
Project 17/5/20191
Project 17/6/20192
Project 17/7/20192
Project 17/8/20193
Project 17/9/20193
Project 28/10/20191
Project 28/11/20192
Project 35/4/20191
Project 35/5/20192
Project 35/6/20193

 

 

Does this help?

 

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.